Distinctive feature of production and warehouse premises consists in complete provision with communications throughout all territory.

 
Electric power supply Carrying capacity of high-voltage line is 151megawatt/hour;
2 main step-down substations of 110/10kV;
44 complete transformer substations of 10/0,4kV;

Length of internal cable runs is 340km;

Water supply 7 artesian wells;
2 pumps with capacity equal to 160m3/h;
5 pumps with capacity equal to 110m3/h;
process water – from Great mainline channel of Toguz water basin;
Gas supply Gas pipeline of 3860 running meters length with carrying capacity equal to 13000m3/ч.
Steam supply Boiler capacity is 150tons per hour.